Quantitative Aptitude · Time, Work & Distance
Time and Work — Questions & Answers
Time-and-work questions treat a job as one whole unit and each worker as a rate — the fraction of the job done per day. Add rates when people work together; subtract for a leak or an opposing worker.
- 5 solved questions
- Step-by-step AI walkthroughs
- Key formulas included
Key formulas
If A finishes a job in a days, A's one day's work is a1
Together: one day's work =a1+b1, so time =a+bab
Men–days: M1D1=M2D2 for the same job (add hours per day as another factor if given)
5 solved Time and Work questions
A can do a piece of work in 10 days and B in 15 days. Working together, in how many days will they finish it?
Solution — answer B
Together their one day's work is 101+151=61, so they finish in 6 days.
4 steps · reveal one at a timeStep 1: **Individual Work Rates**
First, let's find out how much work each person does in one day. If A finishes the work in 10 days, A completes 1/10 of the work per day. Similarly, B completes 1/15 of the work per day.
Step 2: **Combined Daily Work**
When A and B work together, their daily work rates add up. So, their combined work per day is the sum of their individual rates: 1/10+1/15. To add these fractions, find a common denominator, which is 30. This gives us 3/30+2/30=5/30.
Step 3: **Total Time Taken**
The combined daily work simplifies to 5/30=1/6. This means that together, A and B complete 1/6 of the work each day. To find the total number of days they will take to finish the entire work, we take the reciprocal of their combined daily work rate.
Step 4: The answer
So the answer is (B) 6 days. The reciprocal of 1/6 is 6, meaning they will finish the work in 6 days when working together.
A can complete a job in 12 days. He works for 3 days and then leaves. What fraction of the job is left?
Solution — answer C
In 3 days he does 123=41 of the job, so 43 remains.
5 steps · reveal one at a timeStep 1: Daily Work Rate
First, figure out how much of the job A completes in one day. If A finishes the whole job in 12 days, then in one day, A completes 1/12 of the job.
Step 2: Work Done
A works for 3 days. To find the total work A completed, multiply the daily work rate by the number of days worked. Work done =3×(1/12).
Step 3: Simplify Fraction
Simplify the fraction of the job A completed. 3×(1/12)=3/12. This fraction can be simplified by dividing both numerator and denominator by 3, which gives 1/4.
Step 4: Remaining Work
The question asks for the fraction of the job left. If 1/4 of the job is completed, subtract this from the total job (which is 1). Remaining job =1−1/4.
Step 5: The answer
So the answer is (C) 43. When you subtract 1/4 from 1 (or 4/4), you are left with 3/4 of the job.
A and B together can do a job in 8 days, and B alone can do it in 24 days. How long does A alone take?
Solution — answer D
A's one day's work =81−241=121, so A alone takes 12 days.
4 steps · reveal one at a timeStep 1: Understand Work Rates
When solving work problems, it's helpful to think about how much of the job is done in one day. If someone completes a job in X days, their one day's work is 1/X of the total job.
Step 2: Calculate Daily Work
We know A and B together complete the job in 8 days. So, their combined one day's work is 1/8. B alone completes the job in 24 days, meaning B's one day's work is 1/24.
Step 3: Find A's Daily Work
To find how much work A does in one day, we subtract B's daily work from their combined daily work. A's one day's work =81−241.
Step 4: The answer
So the answer is (D) 12 days. Performing the subtraction, A's one day's work is 243−241=242=121. If A does 1/12 of the job per day, A takes 12 days to complete the job alone.
A is twice as efficient as B, and together they finish a job in 12 days. How long does B alone take?
Solution — answer B
If B does 1 unit a day, A does 2, so together 3 units a day. The job is 3×12=36 units, which B alone does in 36 days.
4 steps · reveal one at a timeStep 1: Define efficiency
Let's assume B completes 1 unit of work per day. Since A is twice as efficient as B, A completes 2 units of work per day.
Step 2: Calculate combined rate
When A and B work together, their combined work rate is the sum of their individual rates. This means they complete 1+2=3 units of work per day.
Step 3: Determine total work
They finish the entire job in 12 days, working at a combined rate of 3 units per day. So, the total work required for the job is 3×12=36 units.
Step 4: The answer
So the answer is (B) 36 days. Since B completes 1 unit of work per day, B alone would take 36÷1=36 days to complete the entire job.
A can do a work in 20 days and B in 30 days. They start together, but A leaves 5 days before the work is finished. In how many days is the work completed?
Solution — answer C
If the work ends in T days, A works T−5 days and B works T days: 20T−5+30T=1. Then 3(T−5)+2T=60, so 5T=75 and T=15 days.
5 steps · reveal one at a timeStep 1: Understand work rates
First, let's determine the work rate for each person. A can do the work in 20 days, so A's daily work rate is 1/20. B can do the work in 30 days, so B's daily work rate is 1/30.
Step 2: Define total time
Let T be the total number of days the work is completed. We know A leaves 5 days before the work finishes, so A works for T−5 days. B works for the entire duration, which is T days.
Step 3: Formulate the equation
The total work done is the sum of the work done by A and B. A completes (T−5)/20 of the work, and B completes T/30 of the work. Since the entire work is completed, we set the sum equal to 1: (T−5)/20+T/30=1.
Step 4: Solve for T
To solve for T, find a common denominator (60) and multiply the equation: 3(T−5)+2T=60. This simplifies to 3T−15+2T=60. Combine terms to get 5T−15=60. Add 15 to both sides: 5T=75. Finally, divide by 5 to find T=15 days.
Step 5: The answer
So the answer is (C) 15 days. The calculation shows that the total time taken to complete the work is 15 days, which matches this option.
Free to start
Get exam-ready on Time and Work
Generate fresh time and work practice sets in Test Studio, get step-by-step AI explanations the moment you slip, and close the gaps in Socrative Mode.
- Step-by-step AI solutions
- Fresh practice sets on demand
- Guided Socrative Mode drills